Case study 02 · Cutover & production readiness

A go-live that had been rehearsed twice before it happened

Sixty dependent cutover steps across Basis, functional and integration teams — and a rollback procedure that had never actually been executed.

Anonymised — reconstructed from missions listed in my CV. No client document, figure or outcome is disclosed.

Business contextThe cutover was planned as a single overnight window with dependencies living in a spreadsheet maintained by three people. The rollback section of the plan had been copied from a previous programme.
Challenges
  • Sequencing dependencies held in one person's head
  • Rollback never tested end to end
  • No objective readiness criteria before the window opened
  • Hypercare staffed by guesswork
My responsibilitiesCutover planning and readiness: building the runbook, the rehearsal and the decision criteria.
MethodologyThe plan was rebuilt step by step with an owner, a check and a rollback point per step. Two full rehearsals were run, the second timed, and the readiness gate was defined before the rehearsals rather than after.
Deliverables
  • Cutover runbook with rollback points per step
  • Two timed rehearsal reports
  • Readiness gate criteria
  • Hypercare plan and entry checklist
Business valueThe second rehearsal exposed two ordering faults that would have cost hours in the real window. The go/no-go was taken on evidence, the rollback was never needed — and was executable if it had been.