Case study 03 · S/4HANA / RISE preparation

Preparing a migration without pretending it was a project

RISE migration preparation — prerequisites, dependency mapping and readiness tracking — while the current landscape kept running and releasing every week.

Anonymised — reconstructed from missions listed in my CV. No client document, figure or outcome is disclosed.

Business contextThe programme needed to establish what had to be true before a move to S/4HANA under RISE could even be scoped: which prerequisites were met, what depended on what, and which custom objects had no future.
Challenges
  • Prerequisites scattered across teams with no owner
  • Dependency map missing between custom objects and business processes
  • Migration preparation competing with run-the-business releases
  • Readiness reported as an opinion rather than a status
My responsibilitiesMigration readiness: structuring the prerequisite register, dependency mapping and the reporting that made progress visible.
MethodologyA prerequisite register with an owner and an evidence link per line, a dependency map across custom objects and processes, and a readiness dashboard reviewed in the same governance as the release calendar — so both were planned together.
Deliverables
  • Prerequisite register with owners and evidence
  • Custom object dependency map
  • RISE readiness tracker
  • Monthly readiness dashboard
Business valueThe programme could state its readiness line by line instead of by adjective. Preparation and run-the-business releases were planned on one calendar, which removed the collision that had been silently accepted.